Hillside Road- Safe Routes to Schools Grant

Hillside Road Project Timetable

May 2017

PennDOT has an anticipated December 2017 Bid Opening in their system. Construction would then start spring of 2018, and work along Dupont St. would be completed during the summer months of 2018 while schools are on summer break.

The following submissions have been approved:

Scoping Documents

DEP General Permit 11 (For Bridge Replacement)

CEE Document

Safety Submission

ADA Submission Scoping for Design Build

Traffic/Signing/ Striping Submission

Structural Submission

Utility Submission

ROW Submission – Conditionally Approved – Need School District/Borough Signatures, then Recording

The following submissions have been submitted and are either awaiting comments or being revised:

Chapter 105 Permit – Streambank Stabilization and improvements within the Floodway

Constructability Submission

Format Plan Review

 

The following submission will be sent in once all others are approved Per PennDOT

Plans Specs and Estimate (PS&E) Submission

 

Bid Opening December 2017

 Construction Begin March 2018

 Construction End December 2018

 

Click on the links below to learn more about the Hillside Road- Safe Routes to Schools Grant.

Hillside Road Pedestrian Improvement

Below is a sample photo of the proposed bridge for the Hillside Road- Safe Roads to Schools Grant.

Proposed Bridge for Hillside Road