Ridley Park Borough Tentative Road Repair Schedule

6/22/09

Rodger Street : From Tasker to Thayer, Base repair and mill.

Thayer Street : From Rodgers to Russell, Base repair and mill.

 

6/23/09

Russell Street : From Tasker to Thayer, Base repair and mill.

Thayer Street : From Rodgers to Russell, Base repair and mill.

 

6/24/09 and 6/25/09

Morton Avenue : From Rodgers to Cresswell, Base repair and mill.

 

6/26/09 through 6/29/09

Creswell Street : From Ward to Tasker, Base repair and mill.

 

No work will be done on the weekends.